Data Centers
Completed

OBJECT CHARACTERISTICS:

Facility area: 8,008 m2

Total design capacity: 7.6 MW

IT racks: 880


Specific features of the facility:

  • The first commercial data center in the Far East and the Eastern Siberia certified by Uptime Institute as Tier III
  • The project is being implemented according to the modular technology, in 2 stages:
    • 1st stage includes 2 process modules, with the capacity of 220 racks each, office and amenity building, checkpoint, site improvement and installation of external networks
    • 2nd stage includes other 2 process modules with the total capacity of 440 racks
  • Own operation service 24/7
  • Hosted critical IT infrastructure of federal and regional enterprises
  • The first stage of the data center was launched into operation on February 1, 2023.
  • Commissioning of the 2nd stage is planned for 2025